Tuesday, April 13, 2021

Road Restoration Work

Details of Road Restoration Work

In infrastructure project specifically underground work, required Road Restoration Work (for a new project) before the rainy season. It's necessary to avoid road traffic and road accident also.
Like - Waterline, Drainage line or sewage line, Gas line, Telecommunication line, Electrical Cables

After Road excavation for pipe or cable laying below the ground level, need to excavate a minimum of 1m to 1.5m(it depends on pipe, cable, slop, design, pipe type, pipe quality)

After pipe or cable laying needs to backfill of excavated soil, that soil compact with soil Compactor with compacting by watering the soil and the second alternative is to leave that soil for 10-15days at At least, that method help soil to settle down. earlier the final layer of CC, use to wet edge with water & after Cement Surry both edge of Road for Good bonding with old and new Concrete Layer.

See Full Form 
GSB-Granular sub-base
DLC- a layer of dry lean concrete

CC 200mm(Top Layer)
DLC 150mm(Below CC Layer)
GSB 150mm(Below DLC Layer)
Murum 300mm(Below GSB Layer/Last Layer)
Total Thickness of 800mm

It's little bit vary site to site

Curing is a very important part of this
Guni bags support curing for a long time.
in Summer days need at least 5 times in a day for 10 days
in Winter days need 3-4 times in a day for 10 days. 

Equipment for Road Restoration work
One Bag Concrete Mixture without Hopper(Diesel)
Hand Vibrator Machine Electric
50m Extension wire with industrial safety socket
Level Patti(Aluminum Randa Patti)
Wire Brush








Road Restoration Work

Details of Road Restoration Work In infrastructure project specifically underground work, required Road Restoration Work (for a new project)...